A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the begining and 100 more  after 35 days and completes the work in stipulated time. If he had not  engaged  the additional men, how many days  behind schedule would it be finished?

  • A.3
  • B.5
  • C.6
  • D.9

Answer: B

[(100 x 35) + (200 x 5)]men can finish the work in 1 day 

Therefore, 4500 men can finish the work in 1 day. 100 men can finish it in  4500/100= 45 days.

This is 5 days behind Schedule