Critical Path Net Work helps an engineer

  • A.To concentrate his attention on critical activities
  • B.To divert the resources from noncritical advanced activities to critical activities
  • C.To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
  • D.All of the above

Answer: D