In the beginning, Ram works at a rate such that he can finish a piece of work in 24 hrs, but he only works at this rate for 16 hrs. After that, he works at a rate such that he can do the whole work in 18 hrs. If Ram is to finish this work at a stretch, how many hours will he take to finish this work?

  • A.
    12 hrs
  • B.
    18 hrs
  • C.
    11½ hrs
  • D.
    15 hrs
  • E.22 hrs

Answer: E

Ram’s 16 hr work = 16/24 = 2/3. Remaining work = 1 – 2/3 = 1/3.
Using work and time formula: This will be completed in 1/3 × 18 i.e. 6 hrs.
So, total time taken to complete work = 16 + 6= 22 hrs.