If 10 men can do a piece of work in 12 days, how many men are needed to do the same work in 8 days?

  • A.12 men
  • B.15 men
  • C.18 men
  • D.20 men

Answer: B

This is a man-days problem. We use the formula M1*D1 = M2*D2. Given M1=10, D1=12, D2=8. \(10 \times 12 = M2 \times 8 \Rightarrow 120 = 8 \times M2 \Rightarrow M2 = 120/8 = 15\). So, 15 men are needed.