A and B undertake to do a piece of work for Rs. 600. A alone can do it in 6 days while B alone can do it in 8 days. With the help of C, they finish it in 3 days. Find the share of C.
Answer: A
Wages are distributed in the ratio of the work done. A's 1 day work = 1/6. B's 1 day work = 1/8. (A+B+C)'s 1 day work = 1/3. C's 1 day work = \(1/3 - (1/6+1/8) = 1/3 - 7/24 = (8-7)/24 = 1/24\). Ratio of work done by A:B:C = 1/6 : 1/8 : 1/24. Multiplying by 24 gives the ratio 4:3:1. C's share = \(\frac{1}{4+3+1} \times 600 = \frac{1}{8} \times 600 = 75\). So, C's share is Rs. 75.