A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in:

  • A.5 1/3 days
  • B.6 2/3 days
  • C.8 days
  • D.10 days

Answer: A

LCM of 18 and 24 is 72. Total work = 72 units. A's rate=4, B's rate=3 units/day. Work done in 8 days together = \((4+3) \times 8 = 56\) units. Remaining work = 72 - 56 = 16 units. Time for B to finish this = 16 / 3 = 5 1/3 days.